The Seven Virtues of Reconciling Agile and Earned Worth Administration (EVM)


As extra authorities acquisition packages undertake an Agile improvement methodology, there are extra alternatives for Agile to work together with and maybe deal with earned worth administration (EVM) rules. EVM has been a mainstay inside the U.S. authorities acquisition neighborhood for longer than Agile has, however each are firmly entrenched in coverage that mandates their use. Whereas not all EVM packages are Agile and never all Agile packages use EVM, it’s turning into extra frequent that authorities packages use each strategies. Professionals inside the acquisition neighborhood are normally extra comfy with one methodology than they’re with the opposite, and a few even understand them to be at odds. This notion is maybe forgivable upon examination of the basic assumptions for each practices. This weblog publish will talk about the interactions between Agile and EVM.

To determine potential disconnects and to assist acquirers achieve most profit from these methodologies, we talk about on this publish a few of the variations between Agile and EVM and discover concepts for the way to make them work properly collectively. We summarize the principle supply of incompatibility, perceived or in any other case, as follows:

  • EVM makes an attempt to baseline the mission administration triangle of value, schedule, and efficiency early in a program’s lifecycle. The potential evolution (efficiency) of the system being acquired is mapped over time (schedule) with the labor and supplies (value) wanted to carry out the event. These elements are captured within the efficiency measurement baseline (PMB). This system’s earned worth administration system (EVMS) assesses the precise value and schedule to attain the said efficiency evolution towards the predicted value and schedule that’s baselined within the PMB. Primarily, with this system, the answer is fastened early and the EVMS assesses worth by how properly this system progresses to that answer primarily based on how a lot value and schedule it takes to attain it.
  • Agile inverts this PM triangle as a result of it makes use of cadence-based planning as a substitute of the capability-based planning utilized by EVM. The iterative and glued timeboxes that Agile employs to develop the system being acquired welcome evolutionary modifications within the system’s efficiency as a result of studying is anticipated over time. With Agile, value and schedule are comparatively fastened inside the iterative timeboxes, and the answer that emerges is assessed for worth.

Stephen Wilson-04-1

Determine 1: Conventional Undertaking-Administration Triangle vs. Inverted Agile Triangle

EVM and Agile each vastly affect how a program conducts operations and informs its choices. Agile, although, is extra involved with the method, and EVM is extra involved with measuring the efficiency of that course of, by way of value and schedule. These strategies may and may assist one another. But, anecdotal proof captured in SEI engagements with packages reveals that many packages are struggling to observe Agile improvement processes and precisely measure their progress with EVM.

Acknowledging that each EVM and Agile methods are normally tailor-made to satisfy the wants of every program, we won’t take a one-size-fits-all strategy on this publish to resolve this dilemma. (It is value acknowledging that Agile ideas additionally apply properly to ongoing evolution of a deployed system, the place steady supply fashions are used. In these settings, constructs that derive from Kanban and eXtreme Programming shall be extra distinguished than the acquainted constructs of Scrum. As properly, in these settings, EVM will not be used, or could also be utilized very in a different way.) As an alternative, we’ll spotlight the place SEI workers members have noticed a few of the extra problematic interactions. The next will present some real-world concerns that acquisition professionals ought to concentrate on with Agile and EVM acquisition packages and tasks. Ideally, these concerns can be resolved early in a program’s lifecycle, however they are often encountered all through this system’s evolution.

Large Design Up Entrance (BDUF) Versus Planning as Late as Doable

Conventional acquisition professionals are biased towards planning the way forward for this system with as a lot outlined granularity within the schedule as attainable to assist the varied methods engineering technical critiques (SETRs). The SETRs operate as formal and complete critiques the place this system is meant to convey how properly the design is known and justify the fee and schedule to develop. This strategy encourages a program to forecast a mature, long-term plan and supply the artifacts to assist and defend that plan, manifesting in a plan-driven, fixed-requirements strategy, sometimes called large design up entrance (BDUF). The EVMS measures progress towards that plan, and acquirers consider this system’s success primarily based on its adherence to the plan. This conventional strategy, which is sort of muscle reminiscence to many within the acquisition neighborhood, can discourage program agility all through the efficiency interval when new data, studying, or technological advances could recommend a greater however completely different path ahead.

Conversely, the Agile technique usually presumes that this system doesn’t know as a lot now as it’ll later, and never solely permits but in addition expects options to evolve over time with studying. Program pivots are made as long as evolutionary modifications match inside the comparatively fastened cost-and-schedule guiderails. Sometimes, Agile will use timeboxed planning that has comparatively brief home windows of time to be taught, develop, and consider the answer set. There may be minimal element planning past the present release-planning timebox, sometimes called the program increment/planning interval (PI) or the Agile cadence launch. In the end these two mindsets (conventional acquisition BDUF and Agile) will conflict early in this system, typically as the primary SETR approaches.

These two mindsets could be considered two ends of a planning continuum—large up-front (long-term) planning versus cadence-based short-term planning (generally known as rolling wave planning). A program ought to concentrate on the professionals and cons of every. The EVM mindset is usually related to a BDUF strategy, and it’ll seemingly be extra acquainted to the group’s professionals. However EVM is much less versatile in supporting the answer and necessities flexibility which might be basic to Agile. Profitable packages discover a steadiness between such extremes, and managing progress requires long-term however less-defined high-level plans and short-term element planning captured within the EVMS. It’s finest that this system supervisor, EVM, and engineering communities talk about this continuum early and make sure that they’re synchronized to stop confusion later.

As is normally the case, the optimum strategy lies someplace in between, and it’s situational. Basically, the bigger the viewers or the upper up within the organizational hierarchy that the choice immediately impacts, the earlier the choice and planning needs to be carried out. Usually this case implies that enterprise-wide planning occurs earlier than portfolio planning, and portfolio planning occurs earlier than staff planning. This strategy is especially related with architectural planning choices. As an example, in methods of methods, the architectural plan and imaginative and prescient should be sufficiently outlined up entrance to allow groups to construct appropriate work. Issues like communication protocols, working methods, and timing, which have an effect on the complete enterprise, are finest decided up entrance. However architectural choices that have an effect on solely a single staff needs to be deferred till later to use potential tradeoffs earlier than being documented and applied.

Stephen Wilson-01-1

Determine 2: Hierarchy of Planning Ranges

Assessing Feasibility

Each EVM and Agile improvement place vital emphasis on assessing the feasibility of a program; nevertheless, there are vital variations of their approaches.

For packages that can use EVM, there’s a requirement that an built-in baseline evaluation (IBR) be carried out during which each work and organizational constructions are examined within the context of schedule, finances, and different sources, in addition to any identified dangers. The principle functions of the IBR are to determine further threat and assess whether or not the baseline defines a program that may be achieved. The EVM staff performs a major function in assessing the feasibility of this system. In essence, the IBR is a forward-looking, multi-factor (e.g., value, schedule, efficiency, threat) strategy to assessing feasibility primarily based on the plans developed for this system.

In distinction, Agile packages, notably these following the Lean Startup mannequin, deal with the event of a minimal viable product (MVP), which is a improvement of software program to substantiate or refute the speculation that this system (or some a part of it) is possible. It is an engineering drawback, primarily based on schedule and complexity, to find out when an MVP can and needs to be produced. For the reason that MVP should be constructed first, feasibility is assessed in a backward-looking method to find out whether or not the speculation was sustained.

In massive, complicated packages, an IBR could happen lengthy earlier than an MVP could be developed, notably when the speculation to be examined is of a fancy nature. Furthermore, the IBR considers a broad vary of things whereas the standard MVP is proscribed to answering a smaller set of questions. The MVP, nevertheless, is a concrete demonstration, primarily based on executing code, whereas the IBR is invariably primarily based on projections into the long run.

The 2 approaches are appropriate with one another. For giant packages that can use each Agile strategies and EVM, it’s seemingly that an IBR shall be carried out as typical, although it needs to be thought of that part of the IBR may embrace an illustration of an MVP (if it may be developed in time). Whatever the presence of an MVP, the next questions needs to be answered no later than the IBR:

  • How will the EVM and Agile constructions be aligned in order that the EVM coding constructions [such as the work-breakdown structure (WBS) and organizational breakdown structure (OBS)] are mirrored within the software lifecycle administration device’s hierarchy?
  • How will the Agile roadmap be synchronized with EVM artifacts such because the built-in grasp schedule (IMS)?
  • How are the Agile backlog(s), priorities, and commitments built-in with the approved scope?
  • How will the baseline schedule be aligned with the Agile cadence-based timeboxes?
  • What mechanisms shall be used to replicate Agile studying within the baseline schedule?
  • How will rework be dealt with?

Stephen Wilson-02-1

Determine 3: EVM Plan Vs. Agile Product Viability

How Far Down into the Hierarchy of Agile Work Does the EVMS Observe?

Traditionally, packages have adopted the BDUF technique; not just for the system to be constructed, but in addition for all of the related administration processes. The system isn’t the one factor designed up entrance; so are all organizational and administration constructions. These organizational designs usually observe the organizational assemble and sometimes usually are not seen in Agile developments, although current work in staff topologies suggests mechanisms for organizing the groups based on the specified construction of the system. For each the system and the organizational construction, although, there’s a pressure between primarily fastened constructions in a standard improvement and fluid constructions in an Agile improvement.

An Agile program’s improvement work is damaged down into hierarchical classes primarily based on their ontology. Sometimes, the very best ranges of labor, typically known as epics, would be the overarching capabilities or necessities that may take years to finish. This system will then break down that larger stage work into smaller, extra outlined items that match inside the completely different timeboxed cadence releases and iterations. A generally prescribed hierarchy can be to have epics on the prime, then options, and at last tales on the lowest stage.

Options are normally outlined as element deliberate work that matches inside a program’s Agile cadence launch or PI and offers demonstrable worth. Tales are usually items of labor that may be completed by an Agile staff that match inside an iteration timebox, normally 1 to 4 weeks. Nevertheless, this nominal hierarchy of epicsàfeaturesàstories is usually not practiced. Many packages have greater than three ranges of hierarchy and use completely different terminology and definitions for causes distinctive to them. Usually the terminology will evolve over a program’s improvement lifetime to accommodate altering enterprise and engineering practices.

Stephen Wilson-03a

Determine 4: Nominal Agile Hierarchy and Length to Full

No matter terminology or what number of ranges, all Agile packages can have a breakdown of labor that the EVMS will inevitably should measure. Naturally, some might imagine that the EVMS ought to observe the bottom stage of labor since it’s normally probably the most outlined and element deliberate. Nevertheless, this strategy will seemingly be administratively burdensome and pointless as a result of the bottom stage of labor is simply too detailed for the bigger improvement context. The characteristic stage of labor (utilizing the above paragraph’s nominal hierarchy and terminology) will virtually actually present adequate measurable worth to the general program necessities with out having so as to add so many detail-planned work packages into the PMB.

The very best stage of monitoring is to go no decrease than is important, however low sufficient to achieve the angle wanted for administration to make the correct choices. A program must decide what works for them early and make sure that it may be utilized uniformly. In any other case, disconnects between the enterprise and improvement staff will happen.

Resolving the Stress Between Relative and Absolute Estimation

Estimation is utilized by each EVM and Agile improvement however with completely different objectives in thoughts and, consequently, completely different approaches. In observe neither strategy assumes good estimates. Estimation in EVM is meant to supply administration with an evaluation of how lengthy it’ll take and the way a lot it’ll value to construct a required artifact. Consequently, these estimates are normally given in models of time and prices related to parts to be constructed. Earned worth is then assessed by comparability of precise time and prices together with reported progress to the estimates.

In distinction, in Agile improvement, estimation is used virtually completely for assessing the feasibility of near-term (and team-specific) targets. Nevertheless, these estimates are usually divorced from any models. The staff performing the estimation identifies the smallest work merchandise then assesses all different work gadgets relative to the smallest work merchandise; no models are implied by the estimate. Furthermore, these estimates are usually created on the time work is about to start and never at some interval upfront, as is important for conventional EVM.

For each EVM and Agile, the estimates are primarily based on historic efficiency. Within the case of EVM the historical past comes from previous packages, whereas in Agile the historical past is from current timeboxes. In idea, the Agile estimates needs to be extra correct as a result of they’re primarily based on up-to-date data, however these estimates could be flawed, notably when there may be administration stress to hit schedule targets. A closing consideration is that the standard EVM estimate of effort is usually created in a top-down trend constrained by the ultimate negotiated contract, whereas Agile proponents advocate that the groups develop their estimates with a bottom-up strategy.

Any Agile improvement that can be being tracked with EVM should deal with the difficulty of the way to convert unitless measures to unit-based measures. There are a number of methods this may be completed:

  • Settlement that every level equates to some variety of hours of improvement work–This settlement is usually completed by estimating in “splendid days” as described properly by Mike Cohn in his e book Agile Estimating and Planning. Though this strategy is practiced often, there are downsides to this strategy as a result of it encourages the staff to suppose in absolute moderately than relative estimates. The human mind is nice at relative estimation. For example, contemplate the completely different cup sizes on show on the espresso store; with out realizing absolutely the portions, we will nonetheless rapidly determine which measurement we would like. One other draw back is that splendid days imply that the staff should estimate not solely process measurement but in addition process period, whereas relative estimation is targeted solely on measurement. Chapter 8 of Cohn’s e book is a superb useful resource for extra element on this matter.
  • Utilizing a variable mapping of factors to hours—This mapping might be achieved by summing up all of the factors related to a bit of labor after which dividing absolutely the estimate produced for EVM functions by the factors to get the mapping for this piece of the work. This might require that the Agile staff decide to the preliminary estimate of all of the work, which can discourage studying as the event progresses. Additional, it will be meaningless to match story-point velocities inside a staff from one piece of labor to the following since it will be unlikely that the ratio of hours to factors can be the identical on any two items of labor.
  • Merely ignoring the variations between story factors and hours (or splendid days)—The previous options level out difficulties with reconciling story factors and hours. The query would then come up as to the worth of utilizing two completely different estimation methods that, notably for calculation of progress (p.c full) can be unlikely to offer the identical solutions. Coverage paperwork usually outline the way to use story factors to compute p.c full of a characteristic however give no steering with respect to calculation of prices that might be higher targeted on precise hours vs. deliberate hours for accomplished work. The problem is that, for good causes of consistency, EVM requires that value and schedule efficiency indicators be primarily based on the identical information and models. Subsequently, it might make sense to permit Agile groups and EVM system customers to make use of their very own estimates and never attempt to reconcile them exterior of the context for which they have been meant.

Phrases Matter—Agree Early

Vocabularies are necessary and foster a standard understanding. A shared vocabulary is especially necessary in Agile–EVM discussions for the reason that communities (builders and program administration) are usually new to or not very accustomed to one another’s phrases. If folks don’t take time to develop a standard understanding of phrases, they may imagine that they’ve agreements when, the truth is, they don’t due to completely different interpretations of the phrases used.

Agile and EVM each convey an intensive checklist of not-so-common terminology to an already vocabulary-dense world of DoD acquisitions. It’s seemingly that two events in the identical program have nuanced interpretations of the identical phrase, even after they’ve been on this system for some time. Worse, SEI Agile and EVM practitioners have noticed that the Agile hierarchy phrases and the definitions of every stage generally is a supply of confusion and disconnect. These issues can occur as a result of many packages will evolve their Agile hierarchy by including or eradicating ranges, which is able to drive updates to their definitions. The Agile hierarchy varieties the structure by which the EVMS will consider this system’s improvement progress (see How Far Down into the Hierarchy of Agile Work Does the EVMS Observe?, above). Subsequently, Agile terminology modifications are analogous to engineering modifications, and the operational definition of key phrases could have to be managed in a equally rigorous trend.

A phrase of warning: When frequent Agile phrases, resembling characteristic or epic, are used in a different way, there’s a threat of bewilderment with exterior entities as properly since these phrases are sometimes utilized by different packages.

What’s the Proper Quantity of Administrative Evaluation When Doing Baseline Change Requests (BCRs)?

When an Agile program plans its work for the following cadence launch or PI, work shall be decomposed from the bigger gadgets within the hierarchy, and element planning will happen with probably the most up-to-date data. Normally that is finished collectively throughout the enterprise with subject-matter specialists and stakeholders included for buy-in. The agreed-upon deliberate work then must be captured within the EVMS, which would require baseline change requests (BCRs).

With a standard plan-driven strategy [see Big Design Up Front (BDUF) Versus Planning as Late as Possible, above], BCRs are sometimes considered to be fixes to errors within the plan—they’re deviations from the in any other case long-term plan that isn’t supposed to vary beneath the standard acquisition paradigm. Due to this, the standard BCR course of requires oversight by stakeholders related to the BCR, generally by a BCR board, who evaluation to find out if the change could be made to the PMB. Usually, the specialists which might be required to evaluation and approve the BCR have been current within the PI planning that generated the BCR. Subsequently, this BCR oversight by a board could also be duplicative and pointless, particularly if the EVM material specialists, just like the management account managers (CAMs) and planners, are additionally part of the discharge planning to make sure that EVM guidelines aren’t breached and sudden schedule perturbations don’t happen.

Packages could wish to have two completely different BCR approval processes:

  • A streamlined course of for the planning modifications which might be recognized within the cadence-release/PI planning occasions when all stakeholders are current, and
  • A standard, extra thorough evaluation course of (if wanted) for modifications that happen exterior of the release-planning occasions.

Whatever the approval course of that’s used, it’s additionally necessary to leverage software lifecycle administration instruments and real-time data flows to contain stakeholders in a well timed and environment friendly method, and to make sure that the suitable persons are concerned to approve a BCR.

Assessing Progress

EVM’s worth is derived from its use of precise project-performance information to measure progress. This information is then used to find out the worth of the work accomplished. The simplest and commonest strategy is bodily p.c full. Whereas it’s easy and straightforward to grasp as a result of it’s primarily based on tangible proof of labor completion, it might not contemplate fixed modifications to the scope of the mission, might be topic to interpretation, and will not present a constant view of progress throughout completely different groups.

Inside the Agile philosophy, worth is achieved solely with working software program. Within the strictest implementation, there can be solely two choices: 0 p.c or one hundred pc full. Likewise, EVM steering means that if work packages shall be accomplished inside one reporting cycle, a 0/100 measure of completeness can be applicable.

Massive methods of methods typically require involvement with organizations exterior the management of the software program builders, resembling formal check organizations, certification authorities, platform integration, and so forth. This strategy doesn’t precisely characterize accomplished work and makes accounting for rework troublesome.

On this case, the usage of 0/X/…/Z/100 methodology makes extra sense. Every stage or state is represented with a price of completion agreed to upfront. Packages must decide what the middleman values needs to be. These values function indicators of stage or state completions versus a precise share full.

For instance, if the system required exterior testing and formal certification, a 0/30/75/100 valuation could also be deemed applicable. The work package deal can be decided to be 30 p.c full when it was prepared for the exterior testing. It will then be assessed at 75 p.c after testing and any required rework was accomplished. Lastly, after certification (and any rework) was full, it will be closed out at one hundred pc full.

Setting Up an EVM and Agile Program for Success: The Twain Shall Meet

All these concerns are simply that—concerns. Every program has nuances that can decide what the perfect path ahead is for his or her state of affairs. It’s thrilling to know that there is no such thing as a one precise method to do that, however as a substitute there are seemingly limitless methods to arrange an EVM and Agile program for achievement. The setup could even be extra of an artwork than a science.

Our expertise exhibits that practitioners of EVM and Agile will seemingly encounter all of the tradeoffs detailed on this publish (and possibly extra that weren’t listed). Though there’s not one proper strategy to treatment these, there’s proof that early engagement between EVM and Agile stakeholders can scale back potential for each disciplines to turn into burdensome and as a substitute work collectively to supply helpful perception in managing the outcomes of effort. As with most significant issues in life, groups must adapt by way of the interval of efficiency, so it’s necessary to undertake a studying mindset and arrange the Agile and EVM framework to permit for evolution.

We hope that this weblog publish highlights a few of the necessary commerce areas early for the readers in order that practitioners shall be ready to consider them earlier than they current severe issues. All of the completely different concerns enumerated on this publish underscore the have to be conscious when using Agile and EVM; it’s not simply enterprise as typical. It’s necessary to recollect the intent of Agile and EVM and leverage probably the most helpful parts of every whereas not utilizing the parts that take away from program execution and monitoring. When finished appropriately, practitioners will benefit from the deserves of each practices.